Abstract
With an on-site voltage test it is possible to evaluate polymer insulated cables after laying, repairing or some years in operation. The on-site cable testing can be done easily with frequency tuned series resonant test sets which are still available for testing of medium and high voltage cables. Some tested cables failed after a short time in operation although they had passed the previous voltage test without breakdown. A combination of the voltage test with an additional partial discharge (PD) measurement can increase the test efficiency, but the on-site PD measurement has a lot of difficulties caused by ambient noise. The paper describes results of on-site medium voltage cable testing with a frequency tuned resonant test set and an additional PD measurement with a special PD measuring system.
ASJC Scopus subject areas
- Engineering(all)
- Electrical and Electronic Engineering
- Engineering(all)
- Building and Construction
Cite this
- Standard
- Harvard
- Apa
- Vancouver
- BibTeX
- RIS
In: Conference Record of IEEE International Symposium on Electrical Insulation, Vol. 1, 1996, p. 138-141.
Research output: Contribution to journal › Conference article › Research › peer review
}
TY - JOUR
T1 - On-site cable testing with a resonant test set and an additional partial discharge measurement
AU - Schichler, Uwe
AU - Borsi, H.
AU - Gockenbach, Ernst
N1 - Copyright: Copyright 2004 Elsevier Science B.V., Amsterdam. All rights reserved.
PY - 1996
Y1 - 1996
N2 - With an on-site voltage test it is possible to evaluate polymer insulated cables after laying, repairing or some years in operation. The on-site cable testing can be done easily with frequency tuned series resonant test sets which are still available for testing of medium and high voltage cables. Some tested cables failed after a short time in operation although they had passed the previous voltage test without breakdown. A combination of the voltage test with an additional partial discharge (PD) measurement can increase the test efficiency, but the on-site PD measurement has a lot of difficulties caused by ambient noise. The paper describes results of on-site medium voltage cable testing with a frequency tuned resonant test set and an additional PD measurement with a special PD measuring system.
AB - With an on-site voltage test it is possible to evaluate polymer insulated cables after laying, repairing or some years in operation. The on-site cable testing can be done easily with frequency tuned series resonant test sets which are still available for testing of medium and high voltage cables. Some tested cables failed after a short time in operation although they had passed the previous voltage test without breakdown. A combination of the voltage test with an additional partial discharge (PD) measurement can increase the test efficiency, but the on-site PD measurement has a lot of difficulties caused by ambient noise. The paper describes results of on-site medium voltage cable testing with a frequency tuned resonant test set and an additional PD measurement with a special PD measuring system.
UR - http://www.scopus.com/inward/record.url?scp=0029696361&partnerID=8YFLogxK
M3 - Conference article
AN - SCOPUS:0029696361
VL - 1
SP - 138
EP - 141
JO - Conference Record of IEEE International Symposium on Electrical Insulation
JF - Conference Record of IEEE International Symposium on Electrical Insulation