Abstract
A maintenance problem can be regarded as an optimization task, where the solution is a trade-off between the costs associated with inspection and repair activities and the benefits related to the faultless operation of the infrastructure. The optimization aims at minimizing the total cost while tuning some parameters, such as the number, time, and quality of inspections. Due to the unavoidable uncertainties, the expected cost of maintenance and failure can only be estimated by assessing the reliability of the system. The problem is, therefore, formulated as a time-variant reliability-based optimization, where both objective and constraint functions require the assessment of reliability with time. This paper proposes an efficient general numerical technique to solve this problem by means of just one single reliability analysis, while explicitly taking the diverse forms of uncertainty into account. The technique is generally applicable to any problem where the ageing or damage propagation process is known by means of input-output relationships, which apply to a great number of the cases. This technique exploits a Monte Carlo strategy derived from the concept of forced simulation, which significantly increases the efficiency of computing the optimal solution. The efficiency and accuracy of the proposed approach is shown by means of an example involving a fatigue-prone weld in a bridge girder.
Keywords
- Monte Carlo simulation, Preventive maintenance, Reliability analysis, Scheduling optimization
ASJC Scopus subject areas
- Engineering(all)
- Civil and Structural Engineering
- Engineering(all)
- Building and Construction
- Engineering(all)
- Safety, Risk, Reliability and Quality
Cite this
- Standard
- Harvard
- Apa
- Vancouver
- BibTeX
- RIS
In: ASCE-ASME Journal of Risk and Uncertainty in Engineering Systems, Part A: Civil Engineering, Vol. 3, No. 2, D4016001, 06.2017.
Research output: Contribution to journal › Article › Research › peer review
}
TY - JOUR
T1 - Forced Monte Carlo Simulation Strategy for the Design of Maintenance Plans with Multiple Inspections
AU - De Angelis, Marco
AU - Patelli, Edoardo
AU - Beer, Michael
N1 - Publisher Copyright: © 2016 American Society of Civil Engineers. Copyright: Copyright 2018 Elsevier B.V., All rights reserved.
PY - 2017/6
Y1 - 2017/6
N2 - A maintenance problem can be regarded as an optimization task, where the solution is a trade-off between the costs associated with inspection and repair activities and the benefits related to the faultless operation of the infrastructure. The optimization aims at minimizing the total cost while tuning some parameters, such as the number, time, and quality of inspections. Due to the unavoidable uncertainties, the expected cost of maintenance and failure can only be estimated by assessing the reliability of the system. The problem is, therefore, formulated as a time-variant reliability-based optimization, where both objective and constraint functions require the assessment of reliability with time. This paper proposes an efficient general numerical technique to solve this problem by means of just one single reliability analysis, while explicitly taking the diverse forms of uncertainty into account. The technique is generally applicable to any problem where the ageing or damage propagation process is known by means of input-output relationships, which apply to a great number of the cases. This technique exploits a Monte Carlo strategy derived from the concept of forced simulation, which significantly increases the efficiency of computing the optimal solution. The efficiency and accuracy of the proposed approach is shown by means of an example involving a fatigue-prone weld in a bridge girder.
AB - A maintenance problem can be regarded as an optimization task, where the solution is a trade-off between the costs associated with inspection and repair activities and the benefits related to the faultless operation of the infrastructure. The optimization aims at minimizing the total cost while tuning some parameters, such as the number, time, and quality of inspections. Due to the unavoidable uncertainties, the expected cost of maintenance and failure can only be estimated by assessing the reliability of the system. The problem is, therefore, formulated as a time-variant reliability-based optimization, where both objective and constraint functions require the assessment of reliability with time. This paper proposes an efficient general numerical technique to solve this problem by means of just one single reliability analysis, while explicitly taking the diverse forms of uncertainty into account. The technique is generally applicable to any problem where the ageing or damage propagation process is known by means of input-output relationships, which apply to a great number of the cases. This technique exploits a Monte Carlo strategy derived from the concept of forced simulation, which significantly increases the efficiency of computing the optimal solution. The efficiency and accuracy of the proposed approach is shown by means of an example involving a fatigue-prone weld in a bridge girder.
KW - Monte Carlo simulation
KW - Preventive maintenance
KW - Reliability analysis
KW - Scheduling optimization
UR - http://www.scopus.com/inward/record.url?scp=85045318116&partnerID=8YFLogxK
U2 - 10.1061/AJRUA6.0000868
DO - 10.1061/AJRUA6.0000868
M3 - Article
AN - SCOPUS:85045318116
VL - 3
JO - ASCE-ASME Journal of Risk and Uncertainty in Engineering Systems, Part A: Civil Engineering
JF - ASCE-ASME Journal of Risk and Uncertainty in Engineering Systems, Part A: Civil Engineering
SN - 2376-7642
IS - 2
M1 - D4016001
ER -