Translated title of the contribution | Approaches for determination and reduction of non-productive times of drilling rigs for deep wells |
---|---|
Original language | German |
Journal | Logistics Journal |
Volume | 2013 |
Publication status | Published - 2013 |
Abstract
Because of the high drilling costs an economic power production of deep geothermal energy is currently elusive. Since the production costs of deep wells depend directly on the production time, the non-productive processes require an intensive optimization. Primarily, processes which lead to an interruption of the drilling process will be analyzed and optimized. These processes are mainly the transport of the pipes between rack and working platform as well as the connection process of the pipes. In context of this paper, approaches to redesign the processes and motion sequences for a deep drilling rig are developed and their time savings are investigated.
ASJC Scopus subject areas
- Business, Management and Accounting(all)
- Management Information Systems
- Engineering(all)
- Control and Systems Engineering
- Decision Sciences(all)
- Management Science and Operations Research
Cite this
- Standard
- Harvard
- Apa
- Vancouver
- BibTeX
- RIS
In: Logistics Journal, Vol. 2013, 2013.
Research output: Contribution to journal › Article › Research › peer review
}
TY - JOUR
T1 - Ansätze zur Ermittlung und Reduktion nichtproduktiver Zeiten an Tiefbohranlagen
AU - Bär, Florian
AU - Teodoriu, Catalin
AU - Overmeyer, Ludger
PY - 2013
Y1 - 2013
N2 - Because of the high drilling costs an economic power production of deep geothermal energy is currently elusive. Since the production costs of deep wells depend directly on the production time, the non-productive processes require an intensive optimization. Primarily, processes which lead to an interruption of the drilling process will be analyzed and optimized. These processes are mainly the transport of the pipes between rack and working platform as well as the connection process of the pipes. In context of this paper, approaches to redesign the processes and motion sequences for a deep drilling rig are developed and their time savings are investigated.
AB - Because of the high drilling costs an economic power production of deep geothermal energy is currently elusive. Since the production costs of deep wells depend directly on the production time, the non-productive processes require an intensive optimization. Primarily, processes which lead to an interruption of the drilling process will be analyzed and optimized. These processes are mainly the transport of the pipes between rack and working platform as well as the connection process of the pipes. In context of this paper, approaches to redesign the processes and motion sequences for a deep drilling rig are developed and their time savings are investigated.
KW - Deep geothermal energy
KW - Drilling rig
KW - Non-productive processes
KW - Time saving
UR - http://www.scopus.com/inward/record.url?scp=84886010987&partnerID=8YFLogxK
U2 - 10.2195/lj_Proc_baer_de_201310_01
DO - 10.2195/lj_Proc_baer_de_201310_01
M3 - Artikel
AN - SCOPUS:84886010987
VL - 2013
JO - Logistics Journal
JF - Logistics Journal
SN - 1860-7977
ER -