Details
Originalsprache | Englisch |
---|---|
Titel des Sammelwerks | Vulnerability, Uncertainty, and Risk |
Untertitel | Analysis, Modeling, and Management - Proceedings of the ICVRAM 2011 and ISUMA 2011 Conferences |
Seiten | 805-812 |
Seitenumfang | 8 |
Publikationsstatus | Veröffentlicht - Apr. 2011 |
Extern publiziert | Ja |
Veranstaltung | International Conference on Vulnerability and Risk Analysis and Management, ICVRAM 2011 and the International Symposium on Uncertainty Modeling and Analysis, ISUMA 2011 - Hyattsville, MD, USA / Vereinigte Staaten Dauer: 11 Apr. 2011 → 13 Apr. 2011 |
Publikationsreihe
Name | Vulnerability, Uncertainty, and Risk: Analysis, Modeling, and Management - Proceedings of the ICVRAM 2011 and ISUMA 2011 Conferences |
---|
Abstract
Nowadays, in the areas that are encountered with drinking water shortage, contiguity of sea with land create a facility to change salty water to drinking water using desalination plant and reverse osmosis method. The first desalination project of Iran has been completed in south of Iran in Asalouye. The project contract was registered between Noor Vijeh Company (special joint stock) and Pars Special Economic Energy Zone (PSEEZ) dependent to Oil Ministry of Iran. By this contract, Noor Vijeh Company must deliver 10000 m3/day of drinking water to PSEEZ from the lines of water delivery pipe. Type of the project contract is Build, Operate and Transfer (BOT) scheme within 21 years concession period. Delivered water price is 0.48 euro/m3 in 7 years duration from the beginning of the project and 0.375 euro/m3 for next 13 years. In this paper, the risks of the project are studied and scrutiny and risk management are performed by offering a matrix model. Keyword: Desalination, Build Operate Transfer (BOT), risk management, Project Company, pars special economic energy zone (PSEEZ).
ASJC Scopus Sachgebiete
- Ingenieurwesen (insg.)
- Sicherheit, Risiko, Zuverlässigkeit und Qualität
Zitieren
- Standard
- Harvard
- Apa
- Vancouver
- BibTex
- RIS
Vulnerability, Uncertainty, and Risk: Analysis, Modeling, and Management - Proceedings of the ICVRAM 2011 and ISUMA 2011 Conferences. 2011. S. 805-812 (Vulnerability, Uncertainty, and Risk: Analysis, Modeling, and Management - Proceedings of the ICVRAM 2011 and ISUMA 2011 Conferences).
Publikation: Beitrag in Buch/Bericht/Sammelwerk/Konferenzband › Aufsatz in Konferenzband › Forschung › Peer-Review
}
TY - GEN
T1 - Risk management of asalouye desalination project
AU - Attarzadeh, Meghdad
AU - Chua, David Kim Huat
AU - Beer, Michael
PY - 2011/4
Y1 - 2011/4
N2 - Nowadays, in the areas that are encountered with drinking water shortage, contiguity of sea with land create a facility to change salty water to drinking water using desalination plant and reverse osmosis method. The first desalination project of Iran has been completed in south of Iran in Asalouye. The project contract was registered between Noor Vijeh Company (special joint stock) and Pars Special Economic Energy Zone (PSEEZ) dependent to Oil Ministry of Iran. By this contract, Noor Vijeh Company must deliver 10000 m3/day of drinking water to PSEEZ from the lines of water delivery pipe. Type of the project contract is Build, Operate and Transfer (BOT) scheme within 21 years concession period. Delivered water price is 0.48 euro/m3 in 7 years duration from the beginning of the project and 0.375 euro/m3 for next 13 years. In this paper, the risks of the project are studied and scrutiny and risk management are performed by offering a matrix model. Keyword: Desalination, Build Operate Transfer (BOT), risk management, Project Company, pars special economic energy zone (PSEEZ).
AB - Nowadays, in the areas that are encountered with drinking water shortage, contiguity of sea with land create a facility to change salty water to drinking water using desalination plant and reverse osmosis method. The first desalination project of Iran has been completed in south of Iran in Asalouye. The project contract was registered between Noor Vijeh Company (special joint stock) and Pars Special Economic Energy Zone (PSEEZ) dependent to Oil Ministry of Iran. By this contract, Noor Vijeh Company must deliver 10000 m3/day of drinking water to PSEEZ from the lines of water delivery pipe. Type of the project contract is Build, Operate and Transfer (BOT) scheme within 21 years concession period. Delivered water price is 0.48 euro/m3 in 7 years duration from the beginning of the project and 0.375 euro/m3 for next 13 years. In this paper, the risks of the project are studied and scrutiny and risk management are performed by offering a matrix model. Keyword: Desalination, Build Operate Transfer (BOT), risk management, Project Company, pars special economic energy zone (PSEEZ).
UR - http://www.scopus.com/inward/record.url?scp=79958086594&partnerID=8YFLogxK
U2 - 10.1061/41170(400)98
DO - 10.1061/41170(400)98
M3 - Conference contribution
AN - SCOPUS:79958086594
SN - 9780784411704
T3 - Vulnerability, Uncertainty, and Risk: Analysis, Modeling, and Management - Proceedings of the ICVRAM 2011 and ISUMA 2011 Conferences
SP - 805
EP - 812
BT - Vulnerability, Uncertainty, and Risk
T2 - International Conference on Vulnerability and Risk Analysis and Management, ICVRAM 2011 and the International Symposium on Uncertainty Modeling and Analysis, ISUMA 2011
Y2 - 11 April 2011 through 13 April 2011
ER -